Areas under major construction

Financial assistance program for businesses located in an area affected by major construction

As part of the 2018-2022 business action plan, Montréal launched a financial assistance program in January 2019 for businesses located in areas affected by major construction projects in order to minimize the impacts of construction on their business.

Financial assistance up to $30,000 per fiscal year is calculated according to merchants’ real loss.

Merchants’ loss of gross profit is calculated by comparing the gross profit recorded in any fiscal year during which construction took place with the gross profit recorded during any comparable fiscal year prior to construction. The first 15% of the loss of gross profit for a fiscal year is not covered by the subsidy program.

To apply for the financial assistance program for businesses located in areas affected by major construction projects, you must:

  1. Read by-law RCG 18-043 to fully understand all program conditions
  2. Read our guide to submitting your application to get prepared
  3. Complete the application
  4. Return the following documents along with your completed form:

To reach us or to submit your request, please write us at aidefinanciere@ville.montreal.qc.ca

Eligible areas:

The program is retroactive to January 1, 2016 for city construction sites and to September 21, 2017 for STM construction sites.

Water and sewer pipeline construction

  • Carried out by the city or a neighbouring town
  • After January 1, 2016
  • A minimal planned or real duration of at least six months

Other major public infrastructure projects

  • Carried out by the city or the STM
  • Creates obstructions to automobile traffic
  • A minimal planned or real duration of at least 36 months

List of eligible areas

  • Rue Saint-Denis (Plateau): January 1, 2016 to April 30, 2017
  • Rue Saint-Paul Est (Phase 1): March 1, 2016 to May 31, 2017
  • Rue Notre-Dame Ouest: September 1, 2016 to June 30, 2018
  • Boulevard Laurentien-Rue Lachapelle: December 1, 2016 to June 1, 2019
  • Boulevard Saint-Michel (phase 1): August 1, 2016 to June 30, 2018
  • Rue Sherbrooke Ouest: June 1, 2016 to December 31, 2017
  • Rue Bishop: September 21, 2017 to December 31, 2020 *
  • Rue Jarry Est (Villeray-Saint-Michel-Parc-Extension): August 15, 2016 to May 31, 2018
  • Avenue Laurier Ouest: January 15, 2017 to May 31, 2019
  • Boulevard Saint-Michel (Phase 2): March 13, 2017 to May 31, 2019
  • Avenue Cartier (Pointe-Claire): May 1, 2017 to April 30, 2019
  • Le Triangle: August 7, 2017 to June 30, 2019
  • Rue Sainte-Catherine Ouest: January 8, 2018 to June 30, 2022 *
  • Rue Saint-André (Vélorue): May 9, 2018 to May 31, 2020 *
  • Boulevard Gouin Ouest (Pierrefonds-Roxboro): May 21, 2018 to May 21, 2019
  • Avenue Shamrock: July 9, 2018 to December 31, 2019 *
  • Rue Saint-Hubert: August 20, 2018 to December 31, 2020 *
  • Rue Saint-Paul (Phase 2): May 30, 2018 to July 31, 2019 *
  • Rue Peel (Ville-Marie): May 14, 2018 to February 28, 2020 *
  • Saint-Denis (Villeray-Saint-Michel-Parc-Extension): May 14, 2018 to June 30,2020 *
  • BRT Pie-IX: November 5, 2018 to April 30, 2023

*These dates will be revised to reflect the actual date on which construction ends.

See a map of areas that are eligible for the program here